MOUNT MERRION DEEP RETROFIT
RETROFIT WORKS: | Insulate walls, Heating system, Ventilation, Air-tightness, Heating controls, Re-wiring |
RENOVATION WORKS: | Kitchen, Appliances, Bathroom, Wardrobes, Built in storage, Internal doors and skirting boards, Flooring, Fireplace, Balcony, Painting and decorating |
DESIGN AND PLANNING: | 12 weeks |
CONSTRUCTION: | 10 weeks |
PROJECT DETAILS
Our clients had just purchased this property. It had been rented out for several years and was tired and dated. The building fabric and services were all original so the apartment was cold and uncomfortable.
They lived abroad so didn’t have much time for the design phase, nevertheless they trusted us so two design workshops were sufficient to understand their requirements and propose finishes.
Works commenced with a total strip out followed by new electrics, heating and insulation and re-plastering.
Fit out consisted of all new fittings and finishes to include kitchen, bathroom, storage, internal doors and skirtings, flooring, light fittings and complete decoration. The apartment was handed over in typical RENOVA way, turnkey and ready to use.
The job finished on time and on budget.