Killiney Deep Retrofit Project
RETROFIT WORKS: | Insulated floor slab, Drylining external walls, Roof insulation, Airtightness, Ventilation system, Ait to water heat pump, Underfloor heating, Heating controls, Re-wiring, Low energy lighting, |
FITTINGS & FINISHES: | Layout changes, Kitchen, Utility Room, Kitchen appliances, Bathroom fitouts, Wardrobes, Internal doors, Stairs and balustrade, Skirtings and architraves, Timber floors, Tiled floors, Eaves, Painting and decorating |
STAGES 1 – 5: | 4 months |
STAGE 6: CONSTRUCTION | 30 weeks |
Project details
This was another very typical renovation requests. Our clients had recently purchased this house, and although they had moved in, they wanted to begin and finish their renovation as quickly as possible.
We were on site within in 4 months of first meeting at the house. In that time we agreed a budget, carried out a design process, and selected all finishes and fittings. This was unusually quick and was largely down to the clients enthusiasm to start, and our capacity at the time.
The works went according to plan and the house was handed over on the agreed date. As it happened our clients had a new arrival by the time they moved into their renovated home, so that was nice.