Clonskeagh Deep Retrofit Project

RETROFIT WORKS:Insulated ground floor slab, Insulate external walls (dry lining), Roof insulation, Triple glazed windows and doors, Air tightness, Demand Controlled Ventilation system, Air-to-water heat pump, Central heating with underfloor and aluminium radiators, Heating controls, New plumbing, Rewiring, Energy efficient lighting, Electric fire
FITTINGS AND FINSIHES:Layout changes and extensions, Kitchen including appliances, Bathrooms, Wardrobes, Storage, Internal doors, Skirtings & architraves, Wall panelling, Timber flooring, Tiling, Carpet, Light fittings, Eaves, Gutters & downpipes, Painting and decorating, External step
STAGES 1 – 5:8 months
STAGE 6 (CONSTRUCTION):26 weeks

Our experience with Renova was exceptional. From start to finish, their professionalism and expertise shone through.

They meticulously executed every detail, from the initial planning stages to the final touches, exceeding our expectations at every turn.

Brendan, Sean, Paul, Barbara, Siân and John displayed remarkable skill and dedication, ensuring that the project was completed on time and within budget.

There were numerous times when they went out of their way to get the detail just right and it shows in every corner of our newly renovated home.

We are immensely grateful to Renova for making our dream home a reality.

Project details

Like so many of our client, the owners of this house had bought the house in recent times. It was habitable, albeit cold, so they moved in with the intention of renovating the house as soon as possible. They were referred to RENOVA by friends for whom we had completed a renovation earlier that year. The brief was to modernise the house for comfort and energy efficiency, and to redesign the layout and extend to suit their needs.

We first met in a December to discuss and agree the brief and project budget. We quickly proceed to design and settled on a design and project budget in time for contract signing just 2 months later, in February.

Once the contract was signed, we agreed a start date and arranged workshops. All fittings and finishes were selected before the works started on site and a set of construction drawings prepared. Construction commenced in September and finished 26 weeks later, on time.

This finished house has a BER A2 rating.